Nabavatu relocation delayed to December

Listen to this article:

Rural and Maritime Development Minister Mosese Bulitavu at the Town hall session at Nukubalavu village in Savusavu. Picture: EMA FOSTER

THE relocation of Nabavatu villagers on Vanua Levu has been pushed back again, with the Government now expecting the long-awaited move into permanent homes by December.

The latest delay follows several challenges at the relocation site, including a protest by Pakistani workers.

Speaking at a Town Hall event in Savusavu, Rural and Maritime Development Minister Mosese Bulitavu said the Government had initially been working towards an October completion.

However, Mr Bulitavu said the timeframe had now shifted to December, extending the wait for families who have spent almost five years living in temporary tents.

“The project has faced delays involving construction materials, contractor-related issues, landowner negotiations and ground-strengthening works,” he said.

The Nabavatu relocation project involves the construction of 37 homes, an evacuation centre, church, internal roads, drainage, water and electricity infrastructure.

The project was approved by Cabinet in 2024 at an estimated cost of $5.9million, with the new settlement located at Nadoiviri, about 800 metres from the existing village.

The latest delay means families displaced after Tropical Cyclone Ana in 2021 will remain in temporary accommodation until the new target is met.

n More on the Town Hall discussions — Page 28-29