Approval turnaround times for electrical generation licences have dropped from two to three months to between seven and 14 days following the launch of the Fijian Competition and Consumer Commission’s (FCCC) Electrical Generation Licence Portal.
Responding to questions from The Fiji Times, FCCC chief executive officer Senikavika Jiuta said the manual system previously took up to three months due to extensive checklists, including land documentation and approvals from Energy Fiji Limited (EFL).
“The turnaround time is within 14 days, seven to 14 days through the testing phase. So it’s way faster now depending that they get all the required documents on time,” Ms Jiuta said.
“Whilst they have their documentations, they don’t have to email it across or come down to the office. They can now just come directly and log it into their portal.”
Following soft-launch feedback from electrical contractors who requested a tracking feature to stop back-and-forth follow-ups, FCCC integrated a map into the portal to display licence types, applicants and project locations.
Ms Jiuta confirmed that all 664 existing licences—including businesses with backup generators—had already been migrated onto the portal during the testing period, meaning existing holders do not need to re-apply.
While application lodgements are now digital, licence fee payments remain manual under the first phase of the Market Development Facility (MDF) partnership.
“So we’re moving towards the second phase, which is the payment system. So whilst we’ve got a portal, the payment is still manual.
“So that’s part of the second phase that the payment will now be included into the portal,” she added.
Mandatory physical site inspections by FCCC’s technical team will also remain in place.
Once an application is lodged, it is placed on hold while engineers conduct an independent on-site review with the applicant’s contractors before final approval is granted.
Minister for Industry, Commerce and Business Development Manoa Kamikamica said he was encouraged by the opportunities this initiative would create for local businesses.
“The renewable energy sector provides opportunities for electrical contractors, solar installers, technical service providers and other small and medium enterprises,” he said.
“By simplifying the licensing process, we are reducing the time and administrative burden associated with doing business. This allows enterprises to focus more resources on delivering services, expanding operations and creating employment.”