CONTRACTOR performance and construction challenges remain major concerns in the Cogea relocation project in Bua, according to Fiji Council of Social Services executive director Vani Catanasiga.
Ms Catanasiga said the organisation was aware of residents’ concerns about the slow construction progress and uncertainty surrounding completion of the relocation project.
“We had amended the work program with the contractor at least twice to accelerate progress at the site,” she said.
While responding to queries, she said construction was affected by weather conditions, worker productivity and delays in the delivery of hardware materials.
“There were quite a number of delays from the contractor’s side and these delays were attributed to weather, workers’ productivity and delays in delivery of hardware materials.”
She said there were also difficulties with gravel supplies from the area and timber milling, which was undertaken with the community.
“All these led to FCOSS requesting and being granted two no-cost project extensions throughout the project period from 2023 to 2026.”
However, she said FCOSS remained committed to completing the project.
“FCOSS visited the week before Pre COP to hold discussions with the villagers.
“Out of that meeting, it was decided that Cogea Village would establish a committee to follow up with authorities and monitor works at the Naro site.”
She said FCOSS continued to engage with villagers and potential stakeholders to explore opportunities to fund additional relocation components.