A CONTRACT was signed on August 14 between the Water Authority of Fiji and Appleby Engineering Ltd of New Zealand to ensure a constant supply of water from the Waimanu pumping station.
Under the contract two new standby generators will be installed by Appleby Engineering to ensure that power outages will not affect water supply to the greater Suva-Nausori area.
According to WAF, the current set up standby generators were hired in the event of a power outage – a solution which had become costly in terms of hire and fuel and risky because of the unreliable availability of spare generators.
With the new contract, Appleby Engineering is set to install two new standby generators at the Sawani pumping station to ensure a consistent supply of water to the area.
WAF CEO Opetaia Ravai said the purchase of the generators would cost about $3.4million, and it was a vital addition to the station.
“It will ensure that both the downtime and inconvenience to customers during grid power outages will be minimal,” Mr Ravai said.
“All operating parametres will be thoroughly monitored to ensure the generators are always in good operating condition, so any power shutdown will cause the least disruption to the water supply to our customers.”
Installation is proposed to start in October.
According to company owner John Appleby, the installation would take about 12 weeks to complete.