The high cost of the proposed Nadi Flood Alleviation Project has forced Government to revise its plans, abandoning major infrastructure proposals in favour of more affordable and immediate flood mitigation measures.
Cabinet has endorsed a revised approach after updated technical assessments revealed that the first phase of the proposed major infrastructure alone would cost approximately $693 million.
This exceeds the available project funding of $400 million by $293 million.
The total cost of the broader project could potentially exceed $1 billion, placing it beyond Government’s current financial capacity.
The original proposal included the construction of a diversion channel, the Nadi Town Dyke and other major infrastructure aimed at addressing flooding in Nadi.
However, Cabinet has decided to prioritise lower-cost interventions that can deliver more immediate relief to communities and businesses affected by flooding.
Under the revised approach, Government will focus on expanding the Airport Protection Project and improving drainage systems in Nadi Town and surrounding areas.
Community-based adaptation and nature-based solutions will also continue through the Fiji Climate Adaptation Programme.
These initiatives will be supported by stronger development controls, improved drainage standards and enhanced flood preparedness measures.
Government says the revised strategy is intended to reduce flood impacts on Nadi’s communities, businesses and critical infrastructure in the near to medium term.
The new approach will also focus on strengthening Nadi’s overall resilience to flooding while keeping expenditure within Government’s financial capacity.